Sister Residential Complex: June Construction Progress Update

July 06, 2026

Construction at Sister Residential Complex in Kyiv continues to advance, with the project team completing a number of key milestones throughout June.

In Section 1.1, the reinforced concrete structural frame has been completed. Work is currently underway on the parapet walls surrounding the boiler plant room. Window systems and masonry works have been completed on the second, third and fourth floors.

In Section 1.2, masonry works are continuing on the eighth floor, while installation of the window systems is in progress on the seventh floor. Roofing works are also advancing in parallel.

In Section 1.3, masonry works are likewise progressing on the eighth floor, with window installation underway on the seventh floor. Roofing works continue, alongside the installation of the stormwater drainage system.

In Section 1.4, roofing and masonry works have been completed. Façade works are currently in progress, together with plastering of the common areas and floor screed installation. Construction also continues on the stormwater drainage and electrical distribution networks.

Within the basement areas of the first phase, installation of a high-strength concrete floor with a hardened topping finish has been completed. Installation of the district heating pipeline is also ongoing.

In Section 2.2, construction of the vertical basement structural elements is nearing completion, while vertical waterproofing continues.

In Section 3.1, the basement ceiling slab has been completed, and work has commenced on the vertical structural elements of the ground floor. At the same time, backfilling and vertical waterproofing works remain in progress.

Sister Residential Complex in Kyiv is a contemporary residential development by RIEL, created in line with the Riel Family Style concept to provide a comfortable urban living environment. The project combines thoughtfully designed architecture with on-site amenities, landscaped recreational spaces, retail premises and everyday services — all within easy reach of residents.

Updated purchase terms are currently available. The minimum initial payment starts from 30%, with every buyer receiving a standard 5% discount on the amount of the initial payment. The remaining balance can be paid in interest-free instalments until the completion of construction works.

Apartments in the first construction stage of Sister Residential Complex are also available through Ukraine’s eOselia state-backed mortgage programme, financed by Sky Bank and Ukrgasbank, with interest rates of 3% or 7%, depending on the applicant's eligibility category and the participating bank’s lending terms.

To find the apartment that best suits your needs, visit one of RIEL’s Sales Offices. Contact details are available via the link.

Sister
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.