Brother Residential Complex: Stage 1 Construction Remains on Schedule

July 03, 2026

Construction of Stage 1 at Brother Residential Complex continues to progress according to schedule. The project team is systematically completing each planned stage of construction while moving forward with new works across the development.

In Section A1, the basement plinth-level structural frame and the vertical structural elements of the ground floor have been completed. Waterproofing of the underground retaining walls has also been finalised, followed by backfilling works.

In Section A2, the foundation slab has been cast, while the structural frames of the technical level and plinth level have been completed. In addition, vertical waterproofing of the underground walls has been completed, and backfilling works have been carried out.

In Section A3, concreting of the first, second and third floors has been completed. Work has now commenced on casting the vertical structural elements of the fourth floor.

The stylobate raft foundation slab for the first construction phase has also been completed, and reinforcement of the stylobate’s vertical structural elements is now underway.

Brother Residential Complex is a vibrant new neighbourhood beside Soniachne Lake, inspired by the concept of a Playground — a place where everyday life is active, social and connected. Here, the courtyard is far more than the space between buildings; it is designed as a dynamic environment for movement, recreation, socialising and everyday interaction. A pedestrian promenade runs through the entire neighbourhood, creating a lively route for residents—whether for a morning walk, outdoor exercise or simply relaxing close to home. Open courtyards, shared public spaces, activity areas and well-developed local infrastructure come together to create a community where comfort meets the energy of urban living.

To make purchasing your new home even more accessible, Brother Residential Complex now offers updated purchase terms. The minimum initial payment starts from 30%, with every buyer receiving a standard 5% discount on the amount of the initial payment. The remaining balance can be paid in interest-free instalments until the completion of construction works.

To find the apartment that’s right for you, visit one of RIEL’s Sales Offices. Contact details are available via the link.

Brother
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.