In Stage 1 of the Hyde Park residential complex, wall and corridor reveal finishing (putty works) is ongoing in the common areas, along with tile installation in the corridors and on the stair flights. Masonry works for internal partitions are being carried out in the apartments.
In parallel, screed works have been completed in the commercial premises on the ground floor.
Installation of the individual electricity metering system in the apartments has been completed.
Hyde Park Residential Complex is being developed in a green area of Lviv, at 32 Muchna Street. It is a project designed to help restore life balance and energy. An intimate atmosphere, infrastructure for sports and recreation, panoramic windows, and natural surroundings create a space for harmonious living.