RIEL Real Estate Corporation reports that in the second house of the second stage Ok'Land RC, the installation of showcases for commercial premises is underway, ready by 90%. At the same time, facade works are being performed, 90% completed, common facilities are being finished, 82% ready, and the installation of doors on the first and second floors is 88% complete.
It is also reported that the construction of main sewage pipelines is underway, 74% ready, installation of elevators is 97% completed, screeds are 90% ready, commercial premises are being arranged. The installation of the equipment of the pumping station and external water and sewerage networks are nearing completion, the electrical networks are 70% ready.