Works are ongoing in Stage 3 and of the Novyi Fort residential complex.
Stage 3: In the Section V4, Entrance 3, plastering works in the common areas are continuing. At the same time, finishing works have been completed in two entrances of the Section V4, including installation of plasterboard structures and ceiling re-tensioning.
In the Sections V2 and V3, installation of the internal gas supply networks has been completed. In the Section V3, installation of tiles in the common areas is currently underway.
In the Section V1, installation of railings has been completed, while in Section B2 works on their installation have begun.
Stage 4: In the Section G2, installation of the metal roof structures is ongoing. In the Section G3, works on the installation of plasterboard structures are continuing.
Novyi Fort Residential Complex is a modern residential quarter located within the historic part of Lviv, combining thoughtfully designed layouts, high-quality architecture and a comfortable urban environment for everyday living.