Forward RC: in section B, windows on the ground floor are installed

December 14, 2022

Real Estate Corporation RIEL reports that the construction of Forward RC is in progress. According to the project manager, in section B, the builders are installing windows on the first floor, they have almost completed the arrangement of the facade, the common facilities are being plastered, and the installation of the elevator is being completed. The screeds are completely cast, heat metering units, cold and hot water supply units are being equipped.

In section A, finishing work is being performed in the common facilities, we are continuing the arrangement of internal heat and water supply networks, we are completing the installation of windows on the first floor.

The laying of the walls inside the parking lot has been completed.

You can always find out about the purchase of apartments in Forward RC and the complex construction progress in the sales departments of our company. Contacts are available at the link.

Forward
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.