Forward RC: in section B, the façade arrangement is almost completed

October 18, 2022

RIEL Real Estate Corporation reports that the construction of Forward RC is underway. According to the project manager, in section B, the builders are completing the arrangement of the facade, installed all the windows, have routed electrical networks up to the fifth floor. At the same time, surface casting is being carried out in apartments and common facilities, plastering is being carried out in the common facilities, internal heating and water supply networks are ready from the top to the second floor, and roofing work is in progress.

In section A, the plastering of common facilities has been completed, finishing is being performed. Screed is also made and elevator equipment is ready. Facade work has been completed.

In the parking lot, ventilation and smoke exhaust networks are being arranged, brick partitions are being laid and preparations for the arrangement of entry and exit are being made; work on waterproofing arrangement is being performed.

You can find out all about the purchase of apartments in Forward RC and the complex construction progress in our company sales departments. The addresses are at the link.

Forward
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.