Forward RC: we complete the installation of windows in section B

September 08, 2022

Real Estate Corporation RIEL reports that the construction of Forward RC is underway. According to the project manager, in section B the builders are finishing the installation of window structures, completed the laying of walls, and continue the arrangement of the facade. The screeds are ready from the 11th to the 8th floor, the distribution of heating networks, water supply, electricity and roofing works continues in apartments is 70% ready. The apartment doors have been delivered, installation will begin after the completion of the plastering work.

At the same time, the common facilities plastering is being performed in section A, it has been done from the 3rd to the 11th floor, apartment doors have been delivered, installation will begin after the completion of plastering work. The installation of cooling grid on ventilation ducts is underway, the elevator is fully assembled.

You can find out the information on real property in Forward RC acquisition and information on the complex construction progress, in the sales departments of the company. Contacts are available at the link.

Forward
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.