Forward RC: in section V, the masonry of the walls is being performed

June 14, 2022

RIEL Real Estate Corporation reports that the construction of Forward RC has been fully resumed. According to the project manager, in section V, the masonry of the walls and the monolith of the entrance to the parking lot is being completed.

At the same time, facade work has been restored in section A, screeds are being cast – the fifth to eighth floors are ready, the ninth and tenth floors are is progress. Plumbing and electrical networks are also being arranged.