Forward RC: in section ‘V’, the vertical of the 11th floor is in progress

December 22, 2021

RIEL Real Estate Corporation reports that the construction of Forward RC is pursued. According to the project manager, in section ‘V’, the 10th floor slab casting is over, the vertical of the 11th floor is in progress, the brick laying continues on the second and third floors.

At the same time, in section ‘A’, the roof is 80% completed, horizontal plumbing networks are being rolled out; everything is ready from the fourth to the tenth floor.