Forward RC: in ‘V’ section, the construction of the vertical of the seventh floor is underway

November 10, 2021

RIEL Real Estate Corporation reports that the construction of Forward residential complex is in progress. According to the project manager, in ‘V’ section, the casting of the sixth floor slab has been completed, the arrangement of the seventh floor vertical is in progress.

Meanwhile in section ‘А’, the builders the builders laid insulation, perform screed and lay an intermediate layer of roofing material, then a waterproofing membrane will be installed at the top.

It is also reported that in the building on the fourth and fifth floors, the internal plumbing network and heating systems routing in the apartments are being performed.

In the parking lot, preparations are underway for the arrangement of smoke exhaust and ventilation networks.

Contact the company sales departments for purchase of apartments in Forward RC and information on the complex construction progress, contacts at the link.

Forward
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.