To the news list

Shengen RC: in the fifth house of the second stage, the installation of equipment for a rooftop boiler house is being carried out

July 11, 2023

RIEL Real Estate Corporation reports that the construction of the second stage of Shengen RC is actively pursued. In the house No. 5 of the second stage, the equipment of the roof boiler room is being installed, facade and roofing work, pouring the screed and plastering the walls have been completed.

In the house No. 6, the roof has been completed, windows have been installed, façade work is underway.

At the same time, in the houses No. 8 and 10, laying of tiles in the common facilities has been completed, electrical panels and electricity metres have been installed. Landscaping is underway.

You can find out more about the construction progress and the sale terms for purchasing apartments in Shengen Residential Complex in our sales department. Contacts are at the link.

Shengen
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.