Shengen RC: in the house No. 5 of the second stage, facade work is in progress

January 19, 2023

RIEL Real Estate Corporation reports that the construction of the second stage of Shengen RC is actively pursued. Now, in house No. 5 of the second stage, facade work continues, we are preparing for roof work, we have completed the laying of chimneys and walls of the roof boiler, as well as the ceiling above it. The work on the installation of the heating and water supply system is being completed.

In the house No. 6, the parapets is ready and laying of chimneys has been almost over on the roof; the installation of windows is nearing completion.

At the same time, in the houses No. 8 and 10 tiling in the common facilities is in progress.

You can find out more about the construction progress and the sale terms of purchasing apartments in Shengen RC in our sales department. Contacts at the link.