RIEL Real Estate Corporation reports that the construction of Mіstechko Pidzamche residential complex is actively pursued. In the third stage of Brama complex in section B-2, a foundation pit has been dug and the foundation slab is being arranged. In section B-1, the columns of the first floor are erected and the flights of stairs are arranged. This was announced by the project manager.
In the second stage in section B-4, the installation of sewerage networks has been completed. In section B-1, facade work is being performed, and in sections B-2 and B-3, roof work and fasade construction are underway, as well as the installation of sewer networks.
In the first stage, roof work has been completed, and tiles are being laid in the common facilities.