RIEL REC reports that the construction of Mistechko Pidzamche RC is actively pursued. In the first stage of Brama complex in sections А-1, А-2, А-3, А-4, and А-5, the screeding has been performed in the common facilities, the arrangement of external water and sewerage networks has been completed, the improvement of the adjacent territory is underway. In sections A-3, A-4, A-5, the roof arrangement has been completed, and facade work has been completed in A-4 and A-5. This was announced by the construction project manager.
At the same time, in the second stage in sections B-1 and B-3, the laying of internal and external partitions and the installation of windows have been completed; in sections B-1, B-2, and B-3, the laying of the attic floor has been performed; in sections B-3 and B-4, façade work is underway.
It is also reported that the arrangement of the roof has begun.