Mistechko Pidzamche RC: in the second stage of sections B-1 and B-2 of Novyi Fort RC, preparations are being made for the installation of metres

November 29, 2022

RIEL REC reports that the construction of Mistechko Pidzamche RC is actively pursued. In the second stage of sections B-1 and B-2 of Novyi Fort RC, preparations are being made for the installation of metres, the arrangement of anti-lightning protection has been completed, the improvement of the adjacent territory continues. This was announced by the construction project manager.

At the same time, in the first stage of the section А-1, the waterproofing of the heating plant has been completed, and in sections A-1, A-2, A-3, the installation of switchboard rooms and anti-lightning protection is being completed, metres are also being installed, and the landscaping of the adjacent territory is almost over.

In the third stage, in section B-1, terraces and external sewage networks are being equipped; in sections V-2, V-3, V-4, waterproofing and insulation of terraces is being completed; roofing works are being completed in sections V-2 and V-3; parapets and chimneys on the roof have been erected.

In the fourth stage, in section G-1, the laying of internal walls is being completed and preparations are underway for the installation of the roof; in section G-3, the installation of a wooden roof lathing is being completed.

You can choose a floor and layout and find out other details on the sales terms for purchasing an apartment in Mistechko Pidzamche RC in our sales departments. Contact at the link.

Pidzamche. Novyi Fort
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.