Mistechko Pidzamche RC: in the first stage in section A-1 of Novy Fort complex, equipment for a rooftop boiler house has been installed

October 19, 2022

RIEL Real Estate Corporation reports that Mistechko Pidzamche RC construction is actively pursued. In the first stage in section A-1 of Novy Fort complex, waterproofing of an individual heating plant has been equipped, rooftop boiler house equipment has been installed, improvement of the surrounding grounds is almost over. This was announced by the construction manager.

At the same time, in the second stage, the facade and electricity consumption and control switchboards have been arranged, the installation of anti-lightning protection is being completed, and the landscaping of the adjacent grounds is underway.

In the third stage, terraces are being equipped: waterproofing work and insulation are being performed.

It is also reported that in the fourth stage, the walls have been built in section G-1, preparations for the development of a pit in section G-2 are underway, and work on the arrangement of the roof in section G-3 is in progress.

You can choose the floor and layout, and find out other details about the sales terms for purchasing an apartment in Mistechko Pidzamche RC, in our sales departments. Contacts at the link.

Pidzamche. Novyi Fort
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.