Mistechko Pidzamche. Brama Residential Complex: Construction Progress Update on the Third Stage

May 19, 2026

Construction of the Mistechko Pidzamche. Brama Residential Complex in Lviv is ongoing, and we are pleased to share the latest update on works within the third stage.

In Section B2, wall plastering works in the common areas have been completed. Roof installation works are ongoing, and floor tiling in the common areas has also commenced.

In Section B3, preparations are underway for the installation of internal electrical supply cables and water supply pipes. Façade finishing works are also continuing.

In Section B4, façade works are in progress, alongside preparations for the installation of internal electrical supply cables and water supply pipes.

In Section B5, tile installation on the stair flights is ongoing. At the same time, floor tiling in the common areas and wall plastering in the common areas have already been completed.

In Section B6, roof installation works continue.

Mistechko Pidzamche. Brama Residential Complex is a modern residential quarter located near the centre of Lviv, where contemporary architecture is naturally integrated into the atmosphere of the historic city. The project creates a comfortable environment for everyday living, featuring thoughtfully designed spaces and infrastructure that is always close at hand.

More information about the project, available layouts, and purchase conditions can be obtained from the sales offices. Current contact details are available via the link.

Pidzamche. Brama
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.