Lvivska Ploshcha RC: in the second stage, the installation of lighting devices is carried out

November 12, 2021

RIEL Real Estate Corporation reports that in the second stage, Lvivska Ploshcha RC he installation of lighting devices is carried out. This was announced by the project manager.

Meanwhile, in the first section, the specialists have completed horizontal heating and power supply networks, installed boilers and heating radiators. The arrangement of the smoke exhaust and fire extinguishing system is being completed.

It is also reported that in the second section, water supply and sewerage risers were installed, horizontal routing of the heating and power supply system was performed, boilers and heating radiators have been fully installed. The arrangement of the smoke exhaust and fire extinguishing system is nearing completion.

The parking lot has engineering superstructures and waterproofing, and backfilling.

You can always find out about the terms for the purchase of apartments in the Lvivska Ploshcha RC and the progress of the construction of the complex in the company's sales departments. The addresses are available at the link.

Lvivska Ploshcha