To the news list

Lvivska Ploshcha RC: surface casting in the second stage is completed

August 17, 2021

RIEL Real Estate Corporation reports that the surface casting in the second stage of Lvivska Ploshcha RC is completed. This was announced by the head of the construction project.

Meanwhile, in the first section, the builders completed the installation of water supply and sewerage risers, horizontal heating and power supply networks, and performed the roofing works.

It is also reported that in the second section, the roofing works has been completed by 80%, the arrangement of the smoke removal and fire extinguishing system continues.

The parking lot is equipped with engineering superstructures, 90% ready, as well as waterproofing and backfilling, 50% ready.

You can find out more about the progress of construction and the terms of purchasing an apartment in Lvivska Ploshcha and the progress of the complex construction in our sales departments, contacts at the link.

Lvivska Ploshcha
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.