To the news list

In the third section, the facade works have been completed

October 21, 2021

RIEL Real Estate Corporation reports that the construction of Companion RC is actively pursued. The builders have completed the facade works in the third section. The construction of the boiler house and rainwater drainage networks is underway. This was announced by the construction project manager Viktor Pysarenko.

At the same time, it is reported that in the second section, windows are being installed (90% ready), the facade is being finished (85% ready) and the internal and rainwater drainage is being arranged.

It is also reported that in the first section, the laying of the outer walls of the seventh floor and interior partitions of the fifth and sixth floors is being performed.

You can find out more about the progress of construction and the terms of sale of apartments in Companion RC in our sales departments. Contacts are available at the link.

Companion
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.