Bricklaying of walls completed in section A-1.1

April 17, 2025

In section A-1.1, bricklaying of walls has been completed, pitched roof structures have been erected, and attic windows have been installed. Roof tile installation has begun, and finishing of ventilation chimneys and installation of window structures is ongoing. Interior plastering work has also begun.

In section A-1.2, wall laying continues at the second floor level. At the same time, a sloping roof screed is being laid and sewer pipes are being installed.

In section A-2.2, the excavation work has been completed. Currently, work is underway to reinforce the concrete base for the foundation slab.

Hyde Park is a club house in a cozy area of Lviv that combines privacy, modern architecture, and high-quality construction.

Two green areas around, panoramic windows, a private mini golf course, themed recreation areas – everything is designed for your daily relaxation.

For more information about availability and purchase conditions, please contact the sales department. Contact details are available on the website.

Hyde Park
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.