Engineering networks have been completed in the first building of the second stage of the Companion Residential Complex14.05.2025Read more
Companion RC: installation of water supply engineering networks continues in the second stage of the first building18.04.2025Read more
Companion RC: boilers of the roof boiler house are connected to gas supply in the second phase14.03.2025Read more
Companion Residential Complex: plastering of walls in the basement floor apartments is completed in the second stage of the third building05.02.2025Read more
Companion RC: brickwork of partitions in the basement apartments is completed in the second stage in all buildings20.01.2025Read more
Сompanion Residential Complex: power cables have been installed to the electrical switchboards in all buildings in the second stage24.12.2024Read more
Companion RC: installation of windows in apartments in the second stage of the second building continues20.11.2024Read more
Companion RC: bricklaying of the walls of the basement premises in the second stage of the third building continues20.09.2024Read more