Holoski Kruchi RC: in the first stage, the finishing of staircases has been completed01.08.2023Read more
Holoski Kruchi RC: in the first stage, the installation of the fourth elevator is at the final stage25.04.2023Read more
Holoski Kruchi RC: in the first stage, the installation of railings has been completed08.03.2023Read more
Holoski Kruchi RC: construction of a transformer substation has been completed, installation of equipment is underway22.12.2022Read more
Holoski Kruchi RC: in the second section of the first stage, the installation of entrance doors is in progress25.11.2022Read more
Holoski Kruchi RC: common facilities finishing is being performed in the first section of the second stage24.10.2022Read more
Holoski Kruchi RC: plastering works are being completed in both sections of the first stage15.08.2022Read more
Holoski Kruchi RC: heating and water supply networks are laid in the first section of the first stage13.06.2022Read more