RIEL Real Estate Corporation reports that gates are being installed in the parking lot of house No. 1 of the seventh stage of Velyka Brytaniia RC. This was announced by the construction manager.
At the same time, laying of floor tiles is in progress in the second and third sections of house No. 1. Besides, in the second section on the upper floors, the finishing of the walls has begun, the enclosure of niches in common facilities is underway.
In commercial premises, the installation of a heating system from a roof boiler is being performed.

The landscaping of the local area is in progress.