Riel City RC: in the second stage in section 1, the vertical of the ninth floor is performed

September 07, 2021

RIEL Real Estate Corporation reports that the builders actively pursue the construction of Riel City RC.  They perform the vertical of the ninth floor, the laying is in process on the second floor in the second stage in section 1. This was announced by the project manager.

It is also reported that in section 1-B, the construction of the outer walls has been completed.

Besides, in section 5-A, facade work is being carried out, the readiness is 70%.

At the same time, the builders are carrying out work on the arrangement of commercial premises and completed the concrete monolithic construction of the boiler room.

You can find out more about the progress of construction and the terms of sale of apartments in the Riel City RC in our sales departments, contacts at the link.