Оk`Land RC: in the second section of house No.1, a vertical of 26 floors is performed

November 12, 2021

RIEL Real Estate Corporation reports that the builders go on constructing of house No. 1 of OK'Land RC. Currently, in the second section, a vertical of 26th floor is being carried out, the walls are laid on 13-16 floors.

In the third section, the barrier walls on the roof are reinforced and concreted, and the masonry is laid on 18-20 floors.

Also, according to RIEL employees, monolithic works have been completed in the fourth section, masonry is being performed on 18-20 floors. As for the first section, the barrier walls on the roof are reinforced and concreted, and the masonry is laid on 13-16 floors.