Оk’Land RC: screeds are being poured in the fourth section of building 2

June 04, 2021

Real Estate Corporation RIEL informs that builders continue construction of house No. 2 of OK'Land residential complex. According to the builders, in the fourth section, screeds have been already poured from the fourth to ninth floors, and the facade is being insulated.

Besides, the installation of windows and heating systems reportedly continues in the third section, the screeds have been poured from the fourth to the ninth floors.

Except for that, according to RIEL employees, windows are being installed in the second section, they have been already installed on the third and fourth floors.