Nordica Residence RC: in the first section, the floor slab of the 15th floor is being cast

December 10, 2021

RIEL Real Estate Corporation reports that in the first section of Nordica Residence RC, the floor slab of the 15th floor is being cast, masonry is carried out on the seventh and eighth floors, preparations for arranging the floor of the 1st floor of the parking lot are underway. This was reported by the builders.

In the second section, the pile field has been completed, preparations are underway for the implementation of foundation work, the arrangement of piles for parking is underway.

Besides, it is reported that in the third section, the construction of piles begins.

As to the purchase of apartments in Nordica Residence RC and the progress of the construction of the complex, you can always contact the company's sales departments. Contacts are available at the link.