RIEL Real Estate Corporation reports that the construction of the Mistechko Pidzamche Residential Complex is actively continuing. Currently, façade works are underway in the third stage of the complex in B-2 and B-5 sections.
In B-2 section, walls and internal partitions are being laid, and in B-5 and B-6 sections, the arrangement of chimneys has begun. At the same time, reinforcing belts are being poured in B-6 section, and the parking lot floor slab is being arranged and waterproofing works are underway in B-4 section.

In the second stage, in B-3 section, the laying of internal interior partitions has been completed. Also, flat roofs were filled with gravel in B-1 and B-3 sections.