RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche RC is actively pursued. Now, in 7.1 of the second stage of Vezha complex, construction of the vertical of the fourth floor is being performed. This was announced by the construction project manager.

At the same time, barrier walls are being arranged in section 7.2, and in section 7.3, the seventh floor slab is being cast.

In section 8.1, the builders complete the ceiling slab of the ninth floor.