To the news list

Mistechko Pidzamche RC: in section 6.1 of the second stage of Vezha residential complex, construction of the vertical of the fourth floor continues

September 06, 2021

RIEL Real Estate Corporation reports that the construction of Vezha RC as part of the construction of Mistechko Pidzamche object is actively pursued. In section 6.1 of the second stage of Vezha residential complex, casting of the vertical of the fourth floor continues. This was announced by the head of the construction project Ivan Chykh.

Meanwhile, in section 5.1, in-situ concreting and the erecting of walls have been completed, and in section 4.4, the floor slab of the sixth floor is cast, the vertical of the seventh floor is being performed.

It is also reported that in section 4.3, facade works are underway, and in section 4.2, the walls are fully erected, the facade is in progress, the windows are installed, the roof is completed.

At the same time, in section 4.1, an aluminum facade is being installed and roofing works are being carried out.

You can choose the floor and layout, as well as find out about other details on the terms for purchasing an apartment in Mistechko Pidzamche RC in our sales departments. The contacts are at the link.

Pidzamche. Vezha
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.