To the news list

Mistechko Pidzamche RC: in section 8.1 of the third stage of Vezha complex, the construction of a monolithic frame has been completed

February 22, 2022

RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche object is actively pursued. At present, in section 8.1 of the third stage of Vezha complex, the construction of a monolithic frame has been completed, masonry is in progress. This was announced by the construction project manager.

At the same time, in section 7.1, the vertical of the sixth floor is being erected, and in sections 7.2 and 7.3, the laying of internal and external walls is being performed.

You can choose the floor and layout, and also find out other details on the terms of purchasing an apartment in Mistechko Pidzamche RC at our sales departments. Contacts at the link.

Pidzamche. Vezha
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.