February 22, 2022
RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche object is actively pursued. At present, in section 8.1 of the third stage of Vezha complex, the construction of a monolithic frame has been completed, masonry is in progress. This was announced by the construction project manager.
At the same time, in section 7.1, the vertical of the sixth floor is being erected, and in sections 7.2 and 7.3, the laying of internal and external walls is being performed.