Mistechko Pidzamche RC: in the first stage of section A-2 of Bezha complex, the roof works have been completed

June 17, 2022

RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche RC is actively pursued. In the first stage of section A-2 of Vezha complex, the roof works have been completed. In section A-1, electrical installation works have been completed. At the same time, the heating and water supply networks are ready in sections A-2, A-3 and A-6, and the decoration of the facade is being completed in sections A-4, A-5. This was reported by the construction project manager Ivan Chikh.

In the second stage, in section 4.1, the masonry of the external walls has been completed, and work is ongoing on the inner side of the facade. In section 4.2, the facades and roof have been completed, the heating system is being installed. In section 5.1, all internal networks are mounted, in 4.3 the walls are being bricked up. Section 4.4 is undergoing facade work and windows installing, while walling has been completed in section 6.1.

It is also reported that in the third stage, in section 8.1, the masonry of the nine floors walls has been completed, and the roof work has begun.

In the fifth stage, parapets were cast in section 10.1.

You can choose a floor and layout, and find out other details about the terms of purchasing an apartment in Mistechko Pidzamche RC in our sales departments. Contacts are at the link.

Pidzamche. Vezha
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.