Mistechko Pidzamche RC: in the first stage of New Fort complex, the installation of roof boiler room equipment is almost over

September 25, 2023

Real Estate Corporation RIEL reports that the construction of Mistechko Pidzamche RC is in progress. In the first stage of New Fort complex, the installation of roof boiler room equipment is almost over. In sections A-1, A-2, A-3, the finishing of the walls in the common facilities is at the final stage; at the same time, the builders have installed elevators. At the moment, the installation of decorative ceilings on the first floors and the installation of air pressure and ventilation systems in the common facilities are underway.

In the second stage, in sections B-1 and B-2, the walls in common facilities are being finished, and the installation of elevators and decorative ceilings on the first floors is underway.

In the third stage, in sections B-2 and B-3, the insulation of the facade is in progress, and the installation of rainwater drainage pipes is performed. Facade work begins in section B-1.

In the fourth stage, in section G-1, the installation of window structures is underway; in section G-2, waterproofing of the walls of the basement floor and backfilling of the basement walls have been completed; in section G-3, insulation and finishing of the facade has been completed, and the installation of rainwater drainage pipes has been completed.

You can choose the floor and layout and find out other details on the conditions for purchasing an apartment in Mistechko Pidzamche RC in our sales department. The address is available at the link.

Pidzamche. Novyi Fort
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.