RIEL Real Estate Corporation reports that the construction of Brama residential complex is actively pursued. In sections B-3 и B-4, walls are being laid. At the same time, in section B-1, the laying of internal and external partitions on the fourth and fifth floors is underway, in section B-2, partitions on the first and second floors are being built.

It is also reported that the installation of utilities: internal ventilation and sewerage in sections B-1 and B-2 continues.