February 23, 2022
RIEL Real Estate Corporation reports that the construction of Brama residential complex is actively pursued. In sections B-3 и B-4, walls are being laid. At the same time, in section B-1, the laying of internal and external partitions on the fourth and fifth floors is underway, in section B-2, partitions on the first and second floors are being built.
It is also reported that the installation of utilities: internal ventilation and sewerage in sections B-1 and B-2 continues.
You can choose the floor and layout, and also find out other details on the terms of purchasing an apartment in Mistechko Pidzamche RC at our sales departments. Our managers will be happy to advise you on any issue. Contacts at the link.