Real Estate Corporation RIEL reports that in the second stage of Lvivska Ploshcha RC, tiles are being laid at the entrance groups, the TS (transformer substation) on a permanent basis is being connected, tiles are being paved and the installation of ventilation, smoke exhaust and fire extinguishing systems are almost completed. This was announced by the construction manager.
At the same time, construction of external water supply and sewerage networks are actively pursued.
In the parking lot, the floor is being cast on the -1st floor, and waterproofing is being arranged on the -2nd floor.
You can always find out about the purchase of an apartment in Lvivska Ploshcha RC and the complex construction progress in our company sales departments. Contacts at the link.