Companion RC: in the third section, the laying of internal utility systems is underway

November 19, 2021

RIEL Real Estate Corporation reports that the construction of Companion RC is actively pursued. Specialists in the third section carry out the laying of internal utility systems for water supply, sewerage and heating. Preparations are underway for finishing staircases and common facilities. This was announced by the construction project manager Viktor Pysarenko.

At the same time, it is reported that in the second section, the facade work, the installation of windows and the installation of an internal and rainwater drainage system have been completed.

We also report that in the first section, the walls of the seventh, eighth, ninth floors, and the interior partitions of the sixth and seventh floors are being laid.

You can find out more about the construction progress and terms of sales of apartments in Companion RC at our sales departments. Contacts are available at the link.