Forward RC: in section “B”, the walls are finished in the common facilities

April 06, 2023

RIEL Real Estate Corporation reports that the construction of Forward RC is actively pursued. According to the project management, in section “B”, the walls are finished in the common facilities, preparations are underway for the installation of doors, we are completing roof work and the arrangement of the facade, installation of internal engineering networks is in progress.

In section “A”, we have completed the installation of apartment doors (except for the 11th floor), we are completing the laying of tiles in common facilities, heating radiators have been installed on the ground floor, and moving further up the floors.

In the parking lot, all technical doors are installed in the cells.

You can find out more about the progress of construction and the conditions for sale of apartments in Forward RC in our sales department, contacts at the link.

Forward
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.