To the news list

Facade insulation with slag wool is nearing completion

September 20, 2021

RIEL Real Estate Corporation reports that work on the construction site is actively pursued. Now at the object, the insulation of the facade of the house with slag wool is nearing completion. The project manager Vasyl Cherniukh told us about this.

At the same time, it is reported that foundations for equipment are being made on the roof.

It is also reported that the builders are completing the laying of the partition walls of the house. Sewer risers are ready (except for technical floors).

Meanwhile, horizontal routing of pipes and wires for power grids on the fifth and sixth floors are underway in the house.

It is also reported that the entrance to the parking lot is being arranged.

You can find out more about the terms of purchasing an apartment in Bereh Dnipra RC in the company’s sales departments, contacts at the link.

Bereh Dnipra
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.