In the first stage of Brama complex, the in-situ concreting have been completed

September 06, 2021

RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche residential complex is actively pursued. Now in the first stage of Brama complex, the in-situ concreting have been completed, the total readiness of the erected walls is 80%. This was announced by the head of the construction project.

At the same time, the installation of windows is being carried out, 25% of the total volume is ready, the facades finishing is continuing, more than 15% is ready, the improvement and transfer of the existing city’s networks from the construction footprint are being carried out.