In house No. 3, common facilities are being completed

October 19, 2021

RIEL Real Estate Corporation reports that the builders go on erecting the house No.3 Оk'Land RC. Now in the second, third and fourth sections of the house, plastering of walls in common facilities and installation of a heating and water supply system continues. This was reported in the service department.

Meanwhile, surface casting is performed in the third and fourth sections. In the third section, it is ready from the 3rd to the 24th floor, in the fourth section – from the 3rd to the 10th floor.

It is also reported that the installation of equipment for the gas boiler house is underway.

You can always find out the conditions for the purchase of apartments in OK'Land RC and the status of the construction progress of the complex in the company's sales departments, contacts at the link.