Hyde Park Club House: installation of ventilation ducts and chimneys in section A-1 is in progress

November 19, 2024

RIEL Real Estate Corporation continues to inform about the active construction of the Hyde Park Club House.

The following works are currently underway at the facility: 

  • - installation of ventilation ducts and chimneys in section A-1.1;
  • - brickwork of the fifth floor walls is in progress;
  • - foundation of section A-1.2 has been completed, and the installation of vertical parking lot columns has begun;
  • - construction of the supporting wall of section A-2 is nearing completion.