We continue to share updates on construction works at the Mistechko Pidzamche. Vezha Residential Complex.
Stage 3: In Section 8.1, tiling has been completed in the corridors of common areas, while tiling works continue on stair flights, alongside preparations for final finishing of walls and ceilings. In Section 7.3, lift installation is ongoing; internal finishing works have been completed, installation of stair railings is nearing completion, and the water supply pumping station has been installed. In Section 7.2, installation of internal water supply networks has commenced. In Section 7.1, masonry works for internal walls and partitions are ongoing at the level of the sixth floor.