November 17, 2025

Construction of the Shengen residential complex in Lviv is ongoing. In the Stage III, works are being carried out in the Buildings 9 and 7.

In the Building 9, plastering works have begun, backfilling of the basement levels is underway, and façade works are 90% complete.

In the Building 7, installation of internal engineering networks for heating and water supply continues, and the façade is 70% complete.

In the Stage IV, in Sections B1–C1, construction of the roof above the commercial premises is 60% complete. Installation of aluminium structures has reached 85%, and railing installation is ongoing. Floor tiling in the common areas of the commercial section has been completed. Elevator installation is 70% complete.

In Section B2–C1, installation works to restore the stylobate part are 85% complete, and foundation waterproofing is ongoing. Landscaping works are also in progress on the site, including paving with stone blocks.

The Shengen residential complex by RIEL is a modern comfort-class development located at 7 Zaliznychna Street in Lviv, combining European standards of architecture, functionality, and safety.

For more information on available apartments and purchase conditions, please contact our Sales Department. Contact details are available via the link.

Shengen
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.