Stage 3 Construction Update for August

September 17, 2026

Construction and finishing works are continuing in Stage 3 of the Mistechko Pidzamche. Brama Residential Development in Lviv.

In Section B2, lift installation has been completed.

In Section B4, plastering of the walls in the common areas has been completed, and the lift has been installed.

In Section B5, lift installation has also been completed.

In Section B6, installation of the ventilated façade elements on the mansard floor and installation of the lift have been completed. Flat roof works have also commenced.

Mistechko Pidzamche. Brama is part of RIEL’s large-scale Mistechko Pidzamche development in Lviv. Located close to the city centre, the development combines contemporary architecture, residential and commercial spaces, and thoughtfully designed landscaping.

The development is being created as a complete environment for everyday living, with spaces for relaxation and walking, as well as essential amenities close to home.

Choose your apartment at Mistechko Pidzamche. Brama and find out more about current layouts and purchase terms at RIEL sales offices:

  • Lviv: 116 Bohdana Khmelnytskoho Street or Stryiska Street (2 Persenkivka);
  • Kyiv: 17K Dniprovska Embankment (Bereh Dnipra Residential Development) or 5B Rostyslavska Street (Elyseum Residential Development).
Pidzamche. Brama
We will call you back, advise, select the best options
Thank you for your application! We will contact you shortly.